Installation, commissioning, and testing of the HB650 CM at PIP2IT

2023/08/21 by Michael J. White, J. Makara, White, M +23
Engineering · #Accelerator Physics (physics.acc-ph) #FOS: Physical sciences #Particle Accelerators and Free-Electron Lasers #Particle accelerators and beam dynamics #Superconducting Materials and Applications

paper · pdf · doi:10.48550/arxiv.2308.11036

openalex publication_date 2023/08/21 · openalex created_date 2025/10/10 · openalex updated_date 2026/07/31

Abstract

The Proton Improvement Plan-II (PIP-II) is a major upgrade to the Fermilab accelerator complex, featuring a new 800-MeV Superconducting Radio-Frequency (SRF) linear accelerator (LINAC) powering the accelerator complex to provide the world's most intense high-energy neutrino beam. This paper describes the conversion of the PIP-II Injector Test Facility (PIP2IT) cryogenic system into a test stand for PIP-II High-Beta 650 MHz (HB650) cryomodules at Fermilab's Cryomodule Test Facility (CMTF). A description of the associated mechanical, electrical, and controls modifications necessary for testing HB650 cryomodules are provided. The cooldown and warmup requirements, procedures and associated controls logic is described.

Related